Leather Lead Time for a New Shoe Brand, Week by Week

Most late shoe collections were late before the first prototype: the leather clock was never counted. Here is the clock, stage by stage, and how to run it backwards from your delivery date.

A guide by TL San Martín, a tannery of origin in Elda (Alicante, Spain) since 1995, LWG Gold certified under the Leather Manufacturer standard.

Jorge San Martín · TL San Martín Updated: 2026-11-18 English

For a new shoe brand, leather arrives about 2–4 weeks after confirmation if you buy a stock article in a stock colour, and 3–6 weeks of lab-dip approval later if you need a custom colour. Add freight (2–4 days within the EU, up to 3–5 weeks by sea overseas). Plan backwards from your cutting date, not forwards from today.

A shoe collection is usually planned from the factory backwards: delivery date, cutting date, then "we need the leather by…". The step that gets skipped is the one before: what the tannery needs to put that leather in your hands on that date. At TL San Martín, a tannery in Elda, Spain, certified LWG Gold under the Leather Manufacturer standard (how to read an LWG certificate), the order of events is the same for every new brand, and so are the delays.

How long does leather take to arrive for a new shoe brand?

It depends on one choice: stock colour or custom colour. For a stock article in a stock colour, count roughly 2–4 weeks from order confirmation. A custom colour adds the lab-dip cycle, which takes 3–6 weeks before production even starts. Both figures are the ones we give in your first leather order; the transit time comes on top.

What are the stages, in order?

Stage What happens Typical time
Swatches and colour cardsYou pick the article and colour direction from the libraryFree samples ship in 3–5 working days
Cut sample or lab dipOnly if the colour is custom: the tannery dyes a trial and you approve it3–6 weeks (custom colour only)
Order confirmation and payment termsProforma, deposit or credit terms agreedDays, if the terms were discussed early
Production lotDyeing, finishing, quality check of your lot2–4 weeks, depending on article and finish
FreightPallet or parcel to your factory2–4 days in the EU · 1–2 weeks overseas by air · 3–5 weeks by sea

Two of these rows are the ones founders underestimate: the lab dip, because it needs your approval and a good colour reading, and freight, because the sea route is longer than the production itself.

Why does a custom colour add so much time?

Because the colour is matched on real leather, not on a screen. The tannery dyes a trial piece, you view it under agreed light, you approve or correct, and only then does the lot go into production. Each correction is another round. The way to keep it to one round is a clear reference and a written tolerance, as described in how to sign off a lab dip. If you can accept a colour that already exists in the library, you skip the whole stage; if you need your own, custom colour from crust explains what changes.

How do I plan backwards from the cutting date?

Take the date your factory needs the leather on the cutting table and subtract, in this order: factory receiving buffer (a few days), freight, production lot, order confirmation, lab dip if custom, and finally the sample stage. With a stock colour shipped within the EU, the sum is a few weeks. With a custom colour sent by sea, it is easily three months. A worked example for a colour-critical order:

  1. Cutting date: week 20.
  2. Freight by sea, 3–5 weeks: leave the tannery by week 14–15.
  3. Production lot, 2–4 weeks: confirm by week 10–11.
  4. Lab dip, 3–6 weeks: start by week 4–7.

Write the dates into the order, not only into your calendar.

Where do new brands lose the most time?

Three places, in our experience of first orders. The first is late payment terms: if the deposit is discussed only after the colour is approved, production waits for it; settle the calendar early, as in payment terms for new brands. The second is changing the article after the sample: a different thickness or finish restarts the clock. The third is assuming the second batch is the same as the first: reorders are quick, but the new drum can differ in shade and cost more, which why the second batch costs more explains.

Can I skip the wait with leather already in stock?

Yes, if the article and colour exist as stock. Production lead time for a footwear or bag collection is itself often around 30 to 45 days, so removing the leather wait is the biggest single saving you can make. The trade-off is choice: you buy from what exists. A reserved batch is the middle route, described in leather in stock, catalogue shelf or reserved batch. If the plan includes buying from Spain for the first time, buy leather from Spain covers the route and the paperwork.

Planning a collection and unsure of the dates?

If you are scheduling a first shoe collection and want a second opinion on the leather timeline, post it on the open board under Materials and describe the article, the colour situation and your cutting date. You can also request colour cards and samples on the samples page, and the hub leather for shoes lists the rest of the founder guides.

Frequently asked questions

How long does a first leather order take?

For a stock article in a stock colour, typically 2–4 weeks from confirmation, plus transit. A custom colour adds the lab-dip cycle, so allow 3–6 weeks before production starts.

How long do leather samples take?

Free swatches and colour cards from the library ship from Elda in 3–5 working days. A custom cut sample or lab dip takes longer and follows the colour cycle above. See leather sample costs for what each level includes.

Does freight change the plan?

Yes. Pallet freight inside the EU takes 2–4 days, overseas air 1–2 weeks and sea 3–5 weeks. Sea freight can be longer than the production lot itself, so decide the route before you set the cutting date.

What is the fastest way to a first pair?

Order swatches, choose a stock article in a stock colour, and agree payment terms at the same time. That removes the lab dip and the waiting on a deposit, which are the two longest avoidable delays.

TL San Martín tans and finishes leather in Elda, Alicante, since 1995: LWG Gold under the Leather Manufacturer standard — the only standard under which a Gold medal exists at all; a Trader tops out at “Approved”. Request samples before you specify anything.